Project: Mosaic Village -100kN & 150kN Screw Pile Installation
Year: 2016 Location: Lalor, Victoria Scope of Work: Design, supply, deliver, install, and certify 100kN and 150kN screw piles for Mosaic Village. Value: $300,000.00 Duration: 6 months Challenges: Lalor is recognized for its shallow basalt rock and at this location the basaltic layer has fill material. This project entails jackhammering through shallow basalt rock, excavating and stockpiling the soil, recompacting with engineered fill, digging the footings, and installing, cutting off, and certifying the 100kN and 150kN screw piles.